ASRAMA LELAKI
5 SEPT 2015
___________________________________________________________________________
30 JUN 2015
-----------------------------------------------------------------------------------------------------------
31 MAC 2015
14 MAC 2015
(Pemasangan 'Roof Truses' siap)
(Kerja-kerja mengikat bata diaras 8)
--------------------------------------------------------------------------------------------------------------------
28 FEB 2015
(Pembinaan rasuk bumbung)
(Kerja-kerja mengikat bata di aras 7)
------------------------------------------------------------------------------------------------------------
14 FEB 2015
(Pembinaan tiang untuk 'roof trusses')
(Kerja mengikat bata di aras 6)
---------------------------------------------------------------------------------------------------------
30 JAN 2015
(Pemasangan Papan acuan dan besi tetulang rasuk bumbung dan lantai tangki air sedang dijalankan)
(Kerja-kerja mengikat bata aras 5 sedang dijalankan)
(Kerja-kerja 'wiring' di unit-unit apartment)
(Kerja-kerja pemasangan 'cold water' dan 'sanitary pipe' giat dijalankan di tandas unit apartment)
-----------------------------------------------------------------------------------------------------
13 JAN 2015
(Slab level 9 in progress)
(Brickwall level 3 in progress)
(Installation door frame level 6 in progress)
-------------------------------------------------------------------------------------------------------------
30 DIS 2014
(Slab level 8 100% complete)
(Shear wall level 8 in progress)
(Brick work in Progress- Level 2)
(Install Door frame in Progress)
----------------------------------------------------------------------------------------------------
17 DIS 2014
(Slab level 8 in progress)
-----------------------------------------------------------------------------------------------------
5 DIS 2014
(Aras 6 slab 100 %, shear wall 80%)
(Aras 7 slab 25%)
---------------------------------------------------------------------------------------------------------
13 OKT 2014