SURAU
5 SEPT. 2015
__________________________________________________________________________
30 JUN 2015
---------------------------------------------------------------------------------------------------------
31 MAC 2015
------------------------------------------------------------------------------------------------------
14 MAC 2015
(Tiang 50% siap)
------------------------------------------------------------------------------------------------------------
28 FEB 2015
(Pemadatan tanah untuk kerja-kerja lantai )
----------------------------------------------------------------------------------------------------------------
14 FEB 2015
(Kerja-kerja memasang papan acuan rasuk tanah)
---------------------------------------------------------------------------------------------------------------
30 JAN 2015
(Concreting Pile Caps 50% Completed)
--------------------------------------------------------------------------------------------------------------------
13 JAN 2015
(Kerja-kerja korekan sedang dilaksanakan)
30 DIS 2014
(Tiada Kemajuan)
17 DIS 2014
5 DIS 2014
(Piling work complete 28/11/14)
Nov 2014
Piling work in Progress 70%