ASRAMA PEREMPUAN 1& 2
5 SEPT 2015
_________________________________________________________________________________
30 JUN 2015
ASRAMA PEREMPUAN 1
ASRAMA PEREMPUAN 2
------------------------------------------------------------------------------------------------------------
31 MAC 2015
ASRAMA PEREMPUAN 1
ASRAMA PEREMPUAN 2
----------------------------------------------------------------------------------------------------------
14 MAC 2015
ASRAMA PEREMPUAN 1
(kerja-kerja mengikat bata di aras 6)
('Super structure' 95% siap)
ASRAMA PEREMPUAN 2
(kerja-kerja mengikat bata di aras 5)
('Super structure' 90% siap)
-------------------------------------------------------------------------------------------------------
28 FEB 2015
ASRAMA PEREMPUAN 1
(Kerja-kerja memasang papan acuan lantai tangki air)
(kerja-kerja mengikat bata di aras 5)
ASRAMA PEREMPUAN 2
(Kerja-kerja memasang besi tetulang dan papan acuan aras 9)
(kerja-kerja mengikat bata di aras 3)
---------------------------------------------------------------------------------------------------
14 FEB 2015
ASRAMA PEREMPUAN 1
(Kerja-kerja memasang papan acuan & besi tetulang rasuk bumbung)
(Kerja-kerja mengikat bata di aras 4)
ASRAMA PEREMPUAN 2
(Pembinaan lantai aras 9 sedang dijalankan)
(kerja-kerja mengikat bata diaras 3)
----------------------------------------------------------------------------------------------------------------
30 JAN 2015
ASRAMA PEREMPUAN 1
(Kerja-kerja Pembinaan lantai aras 9 sedang dijalankan)
(Kerja-kerja mengikat bata aras 3 sedang dijalankan)
ASRAMA PEREMPUAN 2
(Kerja-kerja Konkrit Lantai Aras 8 dalam pembinaan)
(Kerja-kerja mengikat bata aras 2 sedang dijalankan)
---------------------------
13 JAN 2015
ASRAMA PEREMPUAN 1
(Slab level 7 complete, shear wall level 7 in progress)
(Brick wall level 2 in progress)
ASRAMA PEREMPUAN 2
(Slab level 7 in progress)
(Brickwall level 2 in progress)
-------------------------------------------------------------------------------------------------------------
30 DIS 2014
ASRAMA PEREMPUAN 1
(Shear wall in Progress)
(Slab level 6, 75% complete)
ASRAMA PEREMPUAN 2
(Slab level 6 , 25% complete)
(Shear wall level 5, 75% complete)
-------------------------------------------------------------------------------------------------------------
17 DIS 2014
ASRAMA PEREMPUAN 1
(Slab level 6 in progress)
ASRAMA PEREMPUAN 2
(Shear wall level 5 in progress)
-----------------------------------------------------------------------------------------------------
5 DIS 2014
ASRAMA PEREMPUAN 1 (Aras 4- 100%)
(Aras 5 - shear wall- 75%)
ASRAMA PEREMPUAN 2 (Aras 4 -100%)
(Aras 5 - slab - 25%)
-----------------------------------------------------------------------------------------------------
13 OKT 2014
ASRAMA PEREMPUAN 1 (Aras 2 -slab 100%, shear wall 25%)
ASRAMA PEREMPUAN 2 (aras 2 - slab 25%