Tarikh Milik Tapak = 26 Ogos 2013
Tarikh Siap = 25 February 2016
Tempoh Kontrak = 30 Bulan
Kemajuan kerja sehingga 31 OGOS 2015
1. Jadual = 59 %
2. Sebenar = 67 %
3. Cepat = 4% (46 hari)
4. Baki Serahan Projek = 178 hari
PROJEK UiTM REMBAU
PROJEK UITM REMBAU
Sunday, 15 March 2015
Saturday, 14 March 2015
KERJA-KERJA LUAR BANGUNAN
5 SEPT 2015
DRAINAGE WORK
SEWERAGE WORK
________________________________________________________________________
30 JUN 2015
SEWERAGE WORK
Kerja-kerja Penggalian dari Manhole MH43 ke MH47
INTERNAL WATER RECTICULATION
Kerja-kerja pemasangan paip MS 150mm
DRAINAGE WORK
ROAD 1
CH 925 TO CH1025
--------------------------------------------------------------------------------------------------------------------
30 APRIL 2015
SEWERAGE WORK
---------------------------------------------------------------------------------------------------------------------
14 MAC 2015
SEWERAGE WORK
Saturday, 14 February 2015
UNIT SUKAN
05 SEPT 2015
30 JUN 2015
05 SEPT 2015
_________________________________________________________________________
30 JUN 2015
--------------------------------------------------------------------------------------------------------------------
31 MAC 2015
-------------------------------------------------------------------------------------------------------------
14 MAC 2015
('Roof Beam' 100% siap)
---------------------------------------------------------------------------------------------------------------
28 FEB 2015
Kerja-kerja memasang 'formwork' rasuk bumbung
------------------------------------------------------------------------------------------------------------
14 FEBRUARY 2015
Kerja kerja korekan untuk penyedian tapak 'Raft Foundation"
Sunday, 1 February 2015
DEWAN PEPERIKSAAN
5 SEPT 2015
31 JUN 2015
--------------------------------------------------------------------------------------------------------------
31 MAC 2015
---------------------------------------------------------------------------------------------------------------
14 MAC 2015
(Pemasangan Besi tetulang 'Raft Foundation' )
--------------------------------------------------------------------------------------------------------------
28 FEB 2015
Pemasangan Besi tetulang untuk 'Raft Foundation'
---------------------------------------------------------------------------------------------------------------
14 FEB 2015
5 SEPT 2015
___________________________________________________________________________
31 JUN 2015
--------------------------------------------------------------------------------------------------------------
31 MAC 2015
---------------------------------------------------------------------------------------------------------------
14 MAC 2015
--------------------------------------------------------------------------------------------------------------
28 FEB 2015
---------------------------------------------------------------------------------------------------------------
14 FEB 2015
Pemasangan Besi Tetulang "Raft Foundation' Mengikut Panel
-------------------------------------------------------------------------------------------------------------
30 JAN 2015
(Penyediaan tapak untuk 'Raft Foundation)
PENGINAPAN PENGURUSAN ASRAMA
5 SEPT 2015
BLOK 1
(Asrama Perempuan 1)
BLOK 2
(Asrama Perempuan 2)
BLOK 3
(Asrama Lelaki)
________________________________________________________________________________
30 JUN 2015
BLOK 1
(Asrama Perempuan 1)
BLOK 2
(Asrama Perempuan 2)
BLOK 3
(Asrama Lelaki)
--------------------------------------------------------------------------------------------------------------
31 MAC 2015
BLOK 1
(Asrama Perempuan 1)
BLOK 2
(Asrama Perempuan 2)
BLOK 3
(Asrama Lelaki)
---------------------------------------------------------------------------------------------------------
14 MAC 2015
BLOK 1
(Asrama Perempuan 1)
(Lantai Aras 2 siap konkrit)
BLOK 2
(Asrama Perempuan 2)
(Korekan untuk 'raft foundation' siap)
BLOK 3
(Asrama Lelaki)
('Super Structure' siap, kerja-kerja mengikat bata dan memasang kerangka pintu bermula)
---------------------------------------------------------------------------------------------------------------
28 FEB 2015
BLOK 1
(Asrama Perempuan 1)
(Persediaan lantai aras 2)
BLOK 3
(Asrama Lelaki)
(Roof beam & slab water tank completed)
-----------------------------------------------------------------------------------------------------
14 FEB 2015
BLOK 1
(Asrama Perempuan 1)
(Kerja-kerja memasang Besi tetulang Rasuk Tanah - Level2)
BLOK 3
(Asrama Lelaki)
(Lantai Aras 4 siap)
-------------------------------------------------------------------------------------------------------
30 JAN 2015
BLOK 1
(Asrama Perempuan 1)
(Kerja-kerja 'pile caps' dalam pembinaan)
BLOK 3
(Asrama Lelaki)
(Tiang aras 3 -50% siap)
-------------------------------------------------------------------------------------------------------------------
13 JAN 2015
BLOK 1
(Asrama Perempuan 1)
BLOK 1
(Asrama Perempuan 1)
(Tiada Kemajuan)
BLOK 3
(Asrama Lelaki)
(Kerja-kerja Konkrit "Raft Foundation" sedia dijalankan)
---------------------------------------------------------------------------------------------------------------
30 DIS 2014
(BLOK 1)
(Asrama Perempuan 1)
BLOK 3
(Asrama Lelaki)
(Kerja-kerja Konkrit "Raft Foundation" sedia dijalankan)
---------------------------------------------------------------------------------------------------------------
30 DIS 2014
(BLOK 1)
(Asrama Perempuan 1)
(Piling work completed)
-----------------------------------------------------------------------------------------------
17 DIS 2014
-----------------------------------------------------------------------------------------------
17 DIS 2014
BLOK 1
(Asrama Perempuan 1)
(Piling work in progress)
Subscribe to:
Posts (Atom)