Saturday, 6 December 2014


SEWERAGE TREATMENT PLANT

5 SEPT 2015


(INTERMEDIATE PUMP SUMP)

______________________________________________________________________________


30 JUN 2015


(INTERMEDIATE PUMP SUMP)


-----------------------------------------------------------------------------------------------------------

31 MAC 2015

(INTERMEDIATE PUMP SUMP)

-------------------------------------------------------------------------------------------------------

14 MAC 2015
(Tiada Kemajuan)

-----------------------------------------------------------------------------------------------------------------

28 FEB 2015
(Tiada Kemajuan)
-------------------------------------------------------------------------------------------------------

14 FEB 2015
(Tiada Kemajuan Selepas Konkrit 'Wall pump Sump')
-----------------------------------------------------------------------------------------------------------------

30 JAN 2015
(Wall Pump Sump Concreting on 27 Jan 2015)
----------------------------------------------------------------------------------------------
13 JAN 2015

(Tiada aktiviti dari 20 dis 2014)

30 DIS 2014
(Wall Pum Sump Waiting For Concreting)


17 DIS 2014
(Installation formwork wall Pump sump)

(Installation & fix rebar wall intermediate Pump Sump)

5 DIS 2014


Monday, 1 December 2014

SURAU

5 SEPT. 2015


__________________________________________________________________________


30 JUN 2015


---------------------------------------------------------------------------------------------------------

31 MAC 2015


------------------------------------------------------------------------------------------------------

14 MAC 2015
(Tiang 50% siap)

------------------------------------------------------------------------------------------------------------


28 FEB 2015

(Pemadatan tanah untuk kerja-kerja lantai )
----------------------------------------------------------------------------------------------------------------


14 FEB 2015
(Kerja-kerja memasang papan acuan rasuk tanah)

---------------------------------------------------------------------------------------------------------------

30 JAN 2015

 (Concreting Pile Caps 50% Completed)

--------------------------------------------------------------------------------------------------------------------
13 JAN 2015

(Kerja-kerja korekan sedang dilaksanakan)

30 DIS 2014
(Tiada Kemajuan)

17 DIS 2014

5 DIS 2014
 (Piling work complete 28/11/14)



Nov 2014
Piling work in Progress 70%

Sunday, 30 November 2014

ASRAMA PEREMPUAN 1& 2

5 SEPT 2015


_________________________________________________________________________________

30 JUN 2015

ASRAMA PEREMPUAN 1


ASRAMA PEREMPUAN 2


------------------------------------------------------------------------------------------------------------

31 MAC 2015

ASRAMA PEREMPUAN 1


ASRAMA PEREMPUAN 2

----------------------------------------------------------------------------------------------------------

14 MAC 2015

ASRAMA PEREMPUAN 1
(kerja-kerja mengikat bata di aras 6)
('Super structure' 95% siap)

ASRAMA PEREMPUAN 2
(kerja-kerja mengikat bata di aras 5)
('Super structure' 90% siap)

-------------------------------------------------------------------------------------------------------

28 FEB 2015

ASRAMA PEREMPUAN 1
(Kerja-kerja memasang papan acuan lantai tangki air)
(kerja-kerja mengikat bata di aras 5)

ASRAMA PEREMPUAN 2
(Kerja-kerja memasang besi tetulang dan papan acuan aras 9)
(kerja-kerja mengikat bata di aras 3)

---------------------------------------------------------------------------------------------------

14 FEB 2015

ASRAMA PEREMPUAN 1
(Kerja-kerja memasang papan acuan & besi tetulang rasuk bumbung)

(Kerja-kerja mengikat bata di aras 4)

ASRAMA PEREMPUAN 2
(Pembinaan lantai aras 9 sedang dijalankan)

(kerja-kerja mengikat bata diaras 3)
----------------------------------------------------------------------------------------------------------------

30 JAN 2015

ASRAMA PEREMPUAN 1

(Kerja-kerja Pembinaan lantai aras 9 sedang dijalankan)
(Kerja-kerja mengikat bata aras 3 sedang dijalankan)

ASRAMA PEREMPUAN 2

(Kerja-kerja Konkrit Lantai Aras 8 dalam pembinaan)
(Kerja-kerja mengikat bata aras 2 sedang dijalankan)

---------------------------
 13 JAN 2015
ASRAMA PEREMPUAN 1

(Slab level 7 complete, shear wall level 7 in progress)

(Brick wall level 2 in progress)


ASRAMA PEREMPUAN 2

(Slab level 7 in progress)


(Brickwall level 2 in progress)



-------------------------------------------------------------------------------------------------------------
30 DIS 2014
ASRAMA PEREMPUAN 1
(Shear wall in Progress)


(Slab level 6, 75% complete)



ASRAMA PEREMPUAN 2
(Slab level 6 , 25% complete)
(Shear wall level 5, 75% complete)

-------------------------------------------------------------------------------------------------------------
17 DIS 2014
ASRAMA PEREMPUAN 1
(Slab level 6 in progress)



ASRAMA PEREMPUAN 2
(Shear wall level 5 in progress)
-----------------------------------------------------------------------------------------------------
5 DIS 2014
ASRAMA PEREMPUAN 1 (Aras 4- 100%)
                                                    (Aras 5 - shear wall- 75%)


ASRAMA PEREMPUAN 2 (Aras 4 -100%)
                                                      (Aras 5 - slab - 25%)

-----------------------------------------------------------------------------------------------------

13 OKT 2014
ASRAMA PEREMPUAN 1 (Aras 2 -slab 100%, shear wall 25%)


ASRAMA PEREMPUAN 2 (aras 2 - slab 25%