Sunday, 30 November 2014

ASRAMA PEREMPUAN 1& 2

5 SEPT 2015


_________________________________________________________________________________

30 JUN 2015

ASRAMA PEREMPUAN 1


ASRAMA PEREMPUAN 2


------------------------------------------------------------------------------------------------------------

31 MAC 2015

ASRAMA PEREMPUAN 1


ASRAMA PEREMPUAN 2

----------------------------------------------------------------------------------------------------------

14 MAC 2015

ASRAMA PEREMPUAN 1
(kerja-kerja mengikat bata di aras 6)
('Super structure' 95% siap)

ASRAMA PEREMPUAN 2
(kerja-kerja mengikat bata di aras 5)
('Super structure' 90% siap)

-------------------------------------------------------------------------------------------------------

28 FEB 2015

ASRAMA PEREMPUAN 1
(Kerja-kerja memasang papan acuan lantai tangki air)
(kerja-kerja mengikat bata di aras 5)

ASRAMA PEREMPUAN 2
(Kerja-kerja memasang besi tetulang dan papan acuan aras 9)
(kerja-kerja mengikat bata di aras 3)

---------------------------------------------------------------------------------------------------

14 FEB 2015

ASRAMA PEREMPUAN 1
(Kerja-kerja memasang papan acuan & besi tetulang rasuk bumbung)

(Kerja-kerja mengikat bata di aras 4)

ASRAMA PEREMPUAN 2
(Pembinaan lantai aras 9 sedang dijalankan)

(kerja-kerja mengikat bata diaras 3)
----------------------------------------------------------------------------------------------------------------

30 JAN 2015

ASRAMA PEREMPUAN 1

(Kerja-kerja Pembinaan lantai aras 9 sedang dijalankan)
(Kerja-kerja mengikat bata aras 3 sedang dijalankan)

ASRAMA PEREMPUAN 2

(Kerja-kerja Konkrit Lantai Aras 8 dalam pembinaan)
(Kerja-kerja mengikat bata aras 2 sedang dijalankan)

---------------------------
 13 JAN 2015
ASRAMA PEREMPUAN 1

(Slab level 7 complete, shear wall level 7 in progress)

(Brick wall level 2 in progress)


ASRAMA PEREMPUAN 2

(Slab level 7 in progress)


(Brickwall level 2 in progress)



-------------------------------------------------------------------------------------------------------------
30 DIS 2014
ASRAMA PEREMPUAN 1
(Shear wall in Progress)


(Slab level 6, 75% complete)



ASRAMA PEREMPUAN 2
(Slab level 6 , 25% complete)
(Shear wall level 5, 75% complete)

-------------------------------------------------------------------------------------------------------------
17 DIS 2014
ASRAMA PEREMPUAN 1
(Slab level 6 in progress)



ASRAMA PEREMPUAN 2
(Shear wall level 5 in progress)
-----------------------------------------------------------------------------------------------------
5 DIS 2014
ASRAMA PEREMPUAN 1 (Aras 4- 100%)
                                                    (Aras 5 - shear wall- 75%)


ASRAMA PEREMPUAN 2 (Aras 4 -100%)
                                                      (Aras 5 - slab - 25%)

-----------------------------------------------------------------------------------------------------

13 OKT 2014
ASRAMA PEREMPUAN 1 (Aras 2 -slab 100%, shear wall 25%)


ASRAMA PEREMPUAN 2 (aras 2 - slab 25%

ASRAMA LELAKI

5 SEPT 2015


___________________________________________________________________________

30 JUN 2015


-----------------------------------------------------------------------------------------------------------

31 MAC 2015



14 MAC 2015
(Pemasangan 'Roof Truses' siap)
(Kerja-kerja mengikat bata diaras 8)

--------------------------------------------------------------------------------------------------------------------

28 FEB 2015
(Pembinaan rasuk bumbung)
(Kerja-kerja mengikat bata di aras 7)

------------------------------------------------------------------------------------------------------------

14 FEB 2015
(Pembinaan tiang untuk 'roof trusses')

(Kerja mengikat bata di aras 6)
---------------------------------------------------------------------------------------------------------

30 JAN 2015

(Pemasangan Papan acuan dan besi tetulang rasuk bumbung dan lantai tangki air sedang dijalankan)
(Kerja-kerja mengikat bata aras 5 sedang dijalankan)

(Kerja-kerja 'wiring' di unit-unit apartment)

(Kerja-kerja pemasangan 'cold water' dan 'sanitary pipe' giat dijalankan di tandas unit apartment)


-----------------------------------------------------------------------------------------------------

 13 JAN 2015

(Slab level 9 in progress)


(Brickwall level 3 in progress)

(Installation door frame level 6 in progress)

-------------------------------------------------------------------------------------------------------------

30 DIS 2014
(Slab level 8 100% complete)
(Shear wall level 8 in progress)



(Brick work in Progress- Level 2)

(Install Door frame  in Progress)



----------------------------------------------------------------------------------------------------

17 DIS 2014
(Slab level 8 in progress)
-----------------------------------------------------------------------------------------------------
5 DIS 2014
(Aras 6 slab 100 %, shear wall 80%)
(Aras 7 slab 25%)

---------------------------------------------------------------------------------------------------------

13 OKT 2014