Saturday, 14 February 2015

UNIT SUKAN

05 SEPT 2015



_________________________________________________________________________


30 JUN 2015



--------------------------------------------------------------------------------------------------------------------

31 MAC 2015


-------------------------------------------------------------------------------------------------------------


14 MAC 2015




('Roof Beam' 100% siap)

---------------------------------------------------------------------------------------------------------------

28 FEB 2015


Kerja-kerja memasang 'formwork' rasuk bumbung

------------------------------------------------------------------------------------------------------------

14 FEBRUARY 2015


Kerja kerja korekan untuk penyedian tapak 'Raft Foundation"


Sunday, 1 February 2015

DEWAN PEPERIKSAAN

5 SEPT 2015



___________________________________________________________________________


31 JUN 2015

--------------------------------------------------------------------------------------------------------------

31 MAC 2015

---------------------------------------------------------------------------------------------------------------

14 MAC 2015


(Pemasangan Besi tetulang 'Raft Foundation' )

--------------------------------------------------------------------------------------------------------------


28 FEB 2015



Pemasangan Besi tetulang untuk 'Raft Foundation'

---------------------------------------------------------------------------------------------------------------

14 FEB 2015



Pemasangan Besi Tetulang "Raft Foundation' Mengikut Panel
-------------------------------------------------------------------------------------------------------------

30 JAN 2015


(Penyediaan tapak untuk 'Raft Foundation)
PENGINAPAN  PENGURUSAN ASRAMA

5 SEPT 2015

BLOK 1
(Asrama Perempuan 1)


BLOK 2
(Asrama Perempuan 2)


BLOK 3
(Asrama Lelaki)



________________________________________________________________________________

30 JUN 2015

BLOK 1
(Asrama Perempuan 1)



BLOK 2
(Asrama Perempuan 2)



BLOK 3
(Asrama Lelaki)




--------------------------------------------------------------------------------------------------------------

31 MAC 2015

BLOK 1
(Asrama Perempuan 1)


BLOK 2
(Asrama Perempuan 2)


BLOK 3
(Asrama Lelaki)

---------------------------------------------------------------------------------------------------------

14 MAC 2015

BLOK 1
(Asrama Perempuan 1)
(Lantai Aras 2 siap konkrit)

BLOK 2
(Asrama Perempuan 2)
(Korekan untuk 'raft foundation' siap)

BLOK 3
(Asrama Lelaki)


('Super Structure' siap, kerja-kerja mengikat bata dan memasang kerangka pintu bermula)

---------------------------------------------------------------------------------------------------------------

28 FEB 2015

BLOK 1
(Asrama Perempuan 1)
(Persediaan lantai aras 2)

BLOK 3
(Asrama Lelaki)

(Roof beam & slab water tank completed)
-----------------------------------------------------------------------------------------------------

14 FEB 2015

BLOK 1
(Asrama Perempuan 1)


(Kerja-kerja memasang Besi tetulang Rasuk Tanah - Level2)

BLOK 3
(Asrama Lelaki)


(Lantai Aras 4 siap)

-------------------------------------------------------------------------------------------------------

30 JAN 2015

BLOK 1
(Asrama Perempuan 1)


(Kerja-kerja  'pile caps' dalam pembinaan)

BLOK 3
(Asrama Lelaki)
(Tiang aras 3 -50% siap)

-------------------------------------------------------------------------------------------------------------------
13 JAN 2015

BLOK 1
(Asrama Perempuan 1)
(Tiada Kemajuan)

BLOK 3
(Asrama Lelaki)
(Kerja-kerja Konkrit "Raft Foundation" sedia dijalankan)

---------------------------------------------------------------------------------------------------------------

30 DIS 2014

(BLOK 1)
(Asrama Perempuan 1)
(Piling work completed)
-----------------------------------------------------------------------------------------------

17 DIS 2014

BLOK 1
(Asrama Perempuan 1)
(Piling work in progress)
BLOK SELENGGARAAN 

5 SEPT 2015


___________________________________________________________________________

30 JUN 2015

------------------------------------------------------------------------------------------------------

31 MAC 2015
-------------------------------------------------------------------------------------------------------------------

14 MAC 2015


(Kerja-kerja melepa dinding siap)

-------------------------------------------------------------------------------------------------------------


28 FEB 2015



(Kerja-kerja melepa dinding dalam bangunan)

---------------------------------------------------------------------------------------------------------------

14 FEB 2015


Kerja kerja melepa dinding luar
----------------------------------------------------------------------------------------------------------

30 JAN 2015

(Penyediaan kerja-kerja Pemasangan Kemasan Bumbung )

----------------------------------------------------------------------------------------------------------------

17 DIS 2014


--------------------------------------------------------------------------------------------

22 NOV 2014