Tarikh Milik Tapak = 26 Ogos 2013
Tarikh Siap = 25 February 2016
Tempoh Kontrak = 30 Bulan
Kemajuan kerja sehingga 31 OGOS 2015
1. Jadual = 59 %
2. Sebenar = 67 %
3. Cepat = 4% (46 hari)
4. Baki Serahan Projek = 178 hari
PROJEK UITM REMBAU
Sunday, 15 March 2015
Saturday, 14 March 2015
KERJA-KERJA LUAR BANGUNAN
5 SEPT 2015
DRAINAGE WORK
SEWERAGE WORK
________________________________________________________________________
30 JUN 2015
SEWERAGE WORK
Kerja-kerja Penggalian dari Manhole MH43 ke MH47
INTERNAL WATER RECTICULATION
Kerja-kerja pemasangan paip MS 150mm
DRAINAGE WORK
ROAD 1
CH 925 TO CH1025
--------------------------------------------------------------------------------------------------------------------
30 APRIL 2015
SEWERAGE WORK
---------------------------------------------------------------------------------------------------------------------
14 MAC 2015
SEWERAGE WORK