PROJECT INFORMATION

Tarikh Milik Tapak               =  26 Ogos 2013

Tarikh Siap                           =  25 February 2016

Tempoh Kontrak                  =  30 Bulan



Kemajuan kerja sehingga 31 OGOS 2015

1. Jadual    = 59 %

2. Sebenar = 67 %

3. Cepat    =   4%  (46 hari)

4. Baki Serahan Projek    =   178 hari