Tarikh Milik Tapak = 26 Ogos 2013
Tarikh Siap = 25 February 2016
Tempoh Kontrak = 30 Bulan
Kemajuan kerja sehingga 31 OGOS 2015
1. Jadual = 59 %
2. Sebenar = 67 %
3. Cepat = 4% (46 hari)
4. Baki Serahan Projek = 178 hari